Rozbiórka i remont budynku Kamienna Góra
Category
🗞
NewsTranscript
00:00 [Polish]
00:02 We have very advanced works aimed at building a communal building.
00:07 The first communal building after 30 years.
00:12 The city has not built anything for such a long time.
00:16 We have a chance to build a building for 24 apartments in a fast method in a modular system.
00:25 The value of this task is about 12 million PLN.
00:30 10.6 million PLN is already recognized from the National Bank of Economy.
00:35 We will have to supplement the remaining amount with either bonds or loans.
00:40 But there is also hope that we will be able to recover the remaining amount in the future.
00:47 If we recover it, and it will happen when the building meets the appropriate heat standards,
00:54 then we can say that we will build 24 apartments for about 200,000 PLN.
01:01 This will be the cost that we as a city will have to bear.
01:06 So it's an absolutely amazing thing.
01:11 If we manage to achieve it in this way,
01:15 we would boast not only about this first building, as I said,
01:20 but also about the exceptionally low costs of its construction.
01:24 This may be achieved next year.
01:28 We could physically finish this work next year,
01:32 if we take care of it this autumn.
01:37 And the chance of this is great.
01:39 Everything is in the hands of the City Council when we turn to them for additional funds.
01:46 In fact, we received an offer for PLN 11,800,000 at the tender,
01:52 so we should be able to deal with the remaining amount.
01:56 you