00:00 The bridge also predicts the future movement of buses and trams.
00:03 At the same time, design work is underway on the design of the tram and bus route,
00:10 from the Sempolno loop, which exists here near the Olympic Stadium,
00:14 to the newly designed Swojczyce loop near Chałupnica Street.
00:20 The design process has been going on for a nice few months
00:24 and we have to admit that last week, sorry, this week,
00:30 we were quite successful and managed to get a decision.
00:34 It was a very important milestone.
00:36 If everything goes well, we would like to submit a report to RID this year.
00:40 We are still waiting for the decision of the Minister of Infrastructure,
00:45 because it has to be the standard that the Minister of Infrastructure
00:50 gives approval for the delay.
00:54 Since this project has been used for a few delays,
00:57 we are waiting for the Minister of Infrastructure's opinion.
01:00 When this opinion is positive, we would like to submit a report to RID this year
01:04 and more or less in the middle of next year,
01:06 we will have this with RID.
01:08 Then the decision of the city authorities
01:10 whether we will announce a tender for construction work
01:13 related to the construction of this tram route.
01:16 That's how it will be next year.