PT Cerestar Indonesia Tbk (TRGU) menargetkan commissioning atau uji kesiapan mesin baru di pabrik Gresik, Jawa Timur dapat dilaksanakan pada Kuartal III-2024. Uji kesiapan mesin baru ini akan berada di bawah kendali anak usaha PT Harvestar Flour Mils.
Category
📺
TVTranscript
00:00PTSRESTAR Indonesia Tbk
00:05The production of wheat flour, PT SERESTAR Indonesia Tbk,
00:09targets the commissioning or test of the new machine preparation
00:12at the Gresik factory in East Java,
00:14which can be carried out in the third quarter of this year.
00:16The test of the new machine preparation
00:18will be under the control of PT HARVESTAR Flower Mills.
00:26PT SERESTAR Indonesia Tbk targets the commissioning
00:29or test of the new machine preparation
00:30at the Gresik factory in East Java,
00:32which can be carried out in the third quarter of this year.
00:34The addition of wheat flour production capacity
00:36is a strategic step to anticipate the dynamic market growth,
00:40especially in meeting the demand for wheat flour
00:43in East Java and its surroundings.
00:45Later, the test of the new machine preparation
00:47will be under the control of PT HARVESTAR Flower Mills.
00:51With a larger wheat flour production capacity,
00:53TRGU will increasingly strengthen its position in this industry
00:56and meet the demand of the market,
00:58so that in the end it will push the growth of wheat production.
01:02With the operation of the new machine,
01:05the production capacity of wheat flour in Gresik
01:07will increase by 600 metric tons per day,
01:10rising from the current production capacity of 1,600 mt per day,
01:14so that the total production capacity will increase to 2,200 mt per day.
01:19In addition to wheat,
01:20TRGU also relies on livestock feed business
01:22to chase the growth of income in 2024.
01:26TRGU's sales continue to show significant increases.
01:29In January 1, 2024,
01:31TRGU managed to freeze an income of Rp 2.9 trillion,
01:35or an increase of 19.8% compared to the same period the year before.