Southbound na bahagi ng Edsa-Kamuning flyover, binuksan muli sa mga motorista

  • last month
Southbound na bahagi ng Edsa-Kamuning flyover, binuksan muli sa mga motorista

Transcript
00:00The southbound of EDSA Kamuning Flyover was opened this morning.
00:04It was opened two months earlier than the original target of October.
00:09But DPWH clarified that the repair of the bridge is not yet finished and its completion rate is only at 30%.
00:16The MMDA and DPWH explained that the repair of the deck slab of the bridge
00:23or the bridge that was passed by the vehicles was already done, that's why it was opened again in Trapico.
00:29For now, the repair of the lower part of the bridge will continue until March 2025.
00:36Retrofitting of the flyover was started in May as a preparation for any calamity such as the flood.