Pj Gubernur Sultra Komjen Pol (Purn) Andap Budhi Revianto minta erbang Jalan Wisata Kendari-Toronipa diaudit.
Category
🗞
NewsTranscript
00:00Governor of South Sulawesi, Andap Budi Revianto, on Friday, September 13, instructed the regional inspectorate of Sultra to conduct an in-depth audit on the construction of the Toro Nipa tourist gate project.
00:15This was done to investigate the damage in some parts of the building, whereas the construction process has not been completed for a long time, since February 2024.
00:28The Toro Nipa tourist gate project is in a mess because it is empty and not made of concrete.
00:35However, it will use GRC building materials or fiber reinforced concrete.
00:41Meanwhile, the construction project itself has swallowed a budget of up to 32 billion rupiah.
00:48The governor also insisted that if there is a violation of the budget of the project, it will be proceeded by the authorities for the next legal process.
01:00I would like to quickly inform the inspectors that there is no time limit.
01:07Of course, it will be investigated and audited by the inspectors.
01:14If there is a violation of the law, as long as it is handled by the authority, the inspectors will handle it.
01:25If there is a violation of the law, it will be handled by the authorities.
01:31He also asked for an objective audit by emphasizing the importance of transparency in the management and allocation of the budget.
01:40From Kendari, Sulawesi, Tenggara, Saharudin, Kantor Berita Antara, Ngowartaken.