Pembangunan Ibu Kota Nusantara masih terus dilakukan. Hingga saat ini, sudah ada 16 paket pekerjaan konstruksi dengan progres rata-rata 87%.

Category

📺
TV
Transcript
00:00Thank you for staying with us, the construction of the capital city of Nusantara is still being carried out.
00:11So far, there have been 16 construction work packages with an average progress of 87%.
00:18Until now, there have been 51 construction workers in the capital city of Nusantara, and there have been 16 construction work packages with an average progress of 87%.
00:36It is noted that there are several buildings built by the private sector that have been completed, namely the Nusantara Hotel, Telkom Smart Office, Peltas IKN 5 MW and the PSSI training center.
00:47There are also several unfinished buildings such as hotels and hospitals built by the private sector.
00:54Deputy Chairperson and Vice Chairperson of the IKN Authority, Danis Hidayat Sumadilaga, revealed the progress of the infrastructure built by the Ministry of Public Works and Public Housing.
01:03Namely, the presidential complex consisting of the Garuda Palace, its progress has reached 99.1%.
01:10The State Palace and the Ceremonial Field, its progress is 87.6%.
01:15As well as the Presidential Secretariat Office, whose progress is already 94%.
01:20There is also the State Secretariat Office, whose progress is already 99.1%.
01:26At the moment, there is also an ecosystem built in 2024 with a 100% infrastructure development progress or has been completed.
01:35This is done by the investors or non-APBN, namely the Nusantara Hotel and the PSSI training center.
01:47Actually, the PSSI training center is a combination of FIFA and APBN.
01:55Then, Telkom Smart Office, Public Transport IP and Peltas IKN 50 MW, which will hopefully be completed soon.
02:05Meanwhile, the construction of the Ministry of Coordinating Offices, the Ministry of Public Works and Public Housing, is still in progress at Kemenco,
02:12and there was a time when President Joko Widodo was in power, which amounted to 4 Kemenco.
02:17The list of development progress is that the Kemenco 1 building is already 94%, Kemenco 2 is already 61.2%,
02:26Kemenco 3 is already 85.4% and the Kemenco 4 building is already 92.1%.
02:34In total, there are 4 buildings in the Kemenco office complex, so there are a total of 16 units.
02:41Jakarta di Beliputan, IDX Channel.