00:00We are carrying out a supervision tour of the construction site to confirm the beginning of the construction work.
00:08We are now in the block that we are going to deliver first, which has 2,400 freeholders.
00:15We are going to deliver it in the middle of next year.
00:19We are doing the work of redecorating the cell,
00:23putting up some walls in the bathrooms to give privacy to the people who are doing their needs in the bathrooms,
00:32so that the others don't see them,
00:34and fixing the work that had to be done so that this is totally freehold.
00:39We are also painting the prison in a different color, because it is a color that complies with the rules.
00:45The rules that are international do not allow the color that had been given to it before,
00:52and we are taking it to the rules.
00:54We are also working on the electrical part, on the sanitary part, on the drinking water part.
01:01Apart from this block, we are working on the administrative block,
01:05which is necessary so that the prison can be operated in a correct way.
01:10After we deliver those two blocks, we are going to continue delivering blocks until we finish the entire prison.
01:16How much is the percentage of the work that has advanced in the totality and in the part that you are going to deliver first?
01:22Well, basically this work has little time, the construction started,
01:27but we can already tell you that the work has started in different workshops.
01:33We have approximately 200 people working here.
01:37The idea is to take it to 300 before the end of the year.
01:40That is done in a coordinated and ordered way, right?
01:44And soon, in the middle of next year, we are going to deliver results.
01:512,400 freeholders, what that can help the penitentiary system is huge.
01:56Half of the prisoners, that is half of the prisoners of La Victoria.
02:02So we are going to give a strong response in the middle of next year.
02:06And we also have the San Juan prison that we are working on, which is 900, which we are going to deliver next year.
02:12We have the one in Barahona, which is 200 more.
02:14We have the one in Anamuya, which is 500 more, which we are also going to deliver next year.
02:19And I think that next year Roberto is going to be very happy with the work that is being done here.
02:24What is missing to conclude here?
02:26Well, everything I told you.
02:28We are adapting the cells so that they can receive people.
02:33There were some jobs that, in terms of design, were poorly implemented.
02:37We are also working in the administrative area.
02:40We are working on the electrical part.
02:42There is a substation that is about to end.
02:46In the sanitary part, in the part of drinking water.
02:50All that is necessary for this prison to function in an orderly way.
02:54The investment at this time, how much is it?
02:56We are talking about all the bids that have been made, approximately 2,400 million pesos.
03:03Perfect, thank you.