00:00In the Koderma Thermal Power Plant,
00:04against ignoring the problems caused by the plant management,
00:10a meeting was held near the KTPS by the proposed committee Banjedi,
00:16in which the problem was not solved.
00:20From 16th January, the decision was taken to shut down the plant.
00:26The committee members, while raising questions on the KTPS work,
00:32held a meeting on the instructions of Amit Yadav.
00:39The committee members said that,
00:42when the construction of this plant had started,
00:46the members of the DVC had made many promises.
00:53But all their promises were false.
00:57The members of the DVC said that,
00:59before the construction of the plant,
01:01it was said that the affected families would be given a job,
01:06electricity, water, health, education, etc.
01:13But even today, the members of the DVC are deprived of all these facilities.
01:18They said that,
01:20earlier, when 1000 MW electricity was generated from the KTPS,
01:26we were worried about the pollution caused by it.
01:30But now, in this case,
01:32the problem will increase if electricity other than 1600 MW is generated.
01:39The developers said that,
01:41if the DVC does not provide facilities under the construction policy,
01:48and does not fulfil our demands,
01:51then we will protest from 16th January.
01:57The Parvhaved Sanghar Committee,
01:59against the DVC,
02:01against the DVC's behavior,
02:03against the promises of the DVC,
02:05today we have to gather the developers here.
02:09The plant has been in operation since 2014.
02:14Look at the condition of the S-Pond,
02:16the condition of the peripheral road,
02:18the education system here,
02:20the pollution here.
02:23The plant has been in operation since 2014.
02:26Look at the condition of the S-Pond.
02:28Through you, we want to warn the DVC,
02:34that if they do not improve their policy,
02:39then we will protest from 16th January.
02:45How many problems are you facing?
02:47The Parvhaved families here,
02:49outside the plant,
02:51look at the condition of the road outside the plant.
02:57Do a survey.
02:59Look at the condition of the road from here to Chandwara.
03:07There is no electricity.
03:09There is no electricity anywhere on the road.
03:11There is no electricity outside the plant.
03:14There is no service for the public.
03:17Look, two days ago,
03:20the Parvhaved Sanghar Committee,
03:22who were sitting here,
03:24when 1000 plants were installed here,
03:26they made a lot of promises.
03:28But none of those promises were fulfilled.
03:33Because of which,
03:35the 1,600 megawatt plant that is coming here,
03:37we are worried about one thing.
03:40There are so many vehicles running at 1,000 megawatts.
03:43When there are 1,600 megawatts left,
03:46there will be a total of 2,600.
03:48How many vehicles will run at 2,600?
03:50We are asking for free education.
03:52All kinds of treatment facilities should be provided in hospitals.
03:55The road from here to Chandwara,
03:57from the plant to Chandwara,
03:59service road, both sides...