00:00I joined on the 17th of January.
00:06As soon as I came here, I got the set down of the canal, which is from 16th to 19th.
00:13On the 17th of January, as soon as we got to know, we cleaned it completely.
00:17It was filled with silt for about 2.5 feet.
00:22We are using as much magnesium as possible.
00:29As soon as the water comes, we will clean it completely.
00:33The bridge has also been damaged a little.
00:35We will repair it and start again.
00:38The capacity of this canal is 19 MLD.
00:42As the silt increases, the capacity decreases.
00:45And the purification of the water system decreases.
00:48The load increases.
00:49So it will work with full capacity.
00:53In the city, we are doing it from 16 Tubil Dhabla and 60 Tubil Gadroop Sagar.
00:58We are doing it for about 72 hours.
01:03It will be ready in 48 hours.
01:06What is your appeal to the common people?
01:08My appeal to the common people is that it was cleaned in 2013.
01:13Now we are cleaning it.
01:15We are working hard to provide clean water.