వైఎస్సార్సీపీ హయాంలో బిల్లులు చెల్లించక నిలిచిన నందివెలుగు పైవంతెన పనులు - పెమ్మసాని చొరవతో మళ్లీ మంచి రోజులు
Category
🗞
NewsTranscript
00:00The Telugu state government, which recognized the necessity of ROB, took action to build a railway station on the way from Guntur to Nandivelugu.
00:16The state government came forward after the railway station to share half of the work.
00:20In 2017, the Telugu state government approved 20 crores.
00:25In the R&B phase, the workers were hired by the tenderer.
00:29On the other hand, the railway station was built on the other side of the track.
00:34In 2019, when the YCP came into power, the workers were paid.
00:39Even though the workers said that they would finish the work only if they were paid, the state government did not care.
00:46The workers who were fed up with this stopped the work.
00:49In 5 years, the work that was done on both sides of the track did not move forward even a bit.
00:53In the R&B phase, 5 pillars were added to 21 slabs.
00:58Due to the delay of the previous government, it looks like it is floating in the air in the newly completed area.
01:05On both sides of the service road, half of the work was done on the drain.
01:09With this, it is a headache not to come on this road.
01:12If the gate falls, the traffic on both sides will increase.
01:17The previous government built this bridge 10 years ago.
01:24The next government will not care about this.
01:28We are very sad about this.
01:30If this bridge is not built, all our villages will be destroyed.
01:35We have to stand at the gates for hours.
01:39We have to wait for hours.
01:42Even if it rains, we cannot stand.
01:45It is very difficult.
01:47We are waiting for your sanctions.
01:49It has been 10 years since the bridge was built.
01:52There was a lot of traffic.
01:54A few days ago, a man had a headache.
01:56He was taken to the hospital urgently.
01:58What should we do?
01:59If we come here, we have to go there.
02:01If the bridge is built soon, we have to go here and there.
02:05It is very difficult to come and go.
02:07It is very difficult to open the gate.
02:09There are many accidents.
02:11If the bridge is built, the people will come for free.
02:14If you do anything, we will be in trouble.
02:19The central government is supportive of the 6th bill.
02:22Shankar Vilas Kudali in Guntur
02:24The central government has agreed to pay 2.5 lakhs for the ring road.
02:27Now, to complete the flyover pending work up to Nandi
02:30The railway authorities have agreed to talk to the PMSA.
02:33To pay 20 crores for this
02:35According to the railway authority
02:37The R&B authority has announced
02:39People are hopeful that their problems will be solved.
02:43It was very difficult in the beginning.
02:45The railway rate fell below.
02:47It has to stop every hour.
02:49It was very difficult when it rained here.
02:52This is the bridge that was built before everything.
02:55Without completing this, they left it.
02:58If there is another 50 crores, all these things will happen.
03:04Shankar Vilas Bridge, Auto Nagar Bridge
03:08300 crores have been sanctioned.
03:11PMSC and NAC have been sanctioned.
03:16Thanks to the Kottam government.
03:19If the gate falls here, I will take the auto.
03:22If the gate falls here, it will take half an hour.
03:25The train will be very scared.
03:28The railway authority has completed the flyover.
03:31The state government is responsible for this.
03:34It's been 7 years, but it's not working.
03:37If there is connectivity, it will be convenient for the people.
03:42When the Telugu party was in power, this flyover was built.
03:47After the YSR Congress Party came,
03:50We are very happy that the Telugu party is in power again.
03:55Also, this flyover should be completed soon.
03:59The tender process is complete.
04:01It will take another 2 months for the work to start again.
04:05Under what circumstances should this flyover be brought to the state?