• 2 days ago
RAIB Grange over Sands, 22 March 2024
Transcript
00:00At around 6.05 on 22nd March 2024, a passenger train travelling at 56mph derailed on the
00:12approach to Grange Oversand station after a void opened in a section of embankment on
00:17which the train was travelling, leading to the rails under the train losing support.
00:23The train was carrying four train crew and four passengers. Nobody was injured but significant
00:28damage was caused to both the train and the railway infrastructure.
00:33Around two days before the derailment, a pipe was damaged during routine maintenance, causing
00:38it to leak water into the embankment. It was this water which dislodged and carried the
00:42material away.
00:45Network Rail had installed the pipe in 2016. It had been fitted into the gaps between the
00:50sleepers as a temporary measure to assist in managing flood water in the surrounding
00:54areas.
00:56The nature of the embankment's construction meant that water leaking from the pipe was
01:00prevented from leaving its seaward side and was redirected to landwards. This allowed
01:05piping to form, transporting sand and silt away from the embankment. As a result, a void
01:11formed underneath the track and material continued to be carried away. Eventually, the material
01:17over the void collapsed under the passing train.
01:21The damage to the pipe was immediately reported to the relevant railway control room by the
01:25maintenance staff on site, but due to ineffective communications, no action was taken to stop
01:31a pump which was supplying water to it.
01:34As a result of the investigation, REIB has made five recommendations. Three recommendations
01:40are made to Network Rail. These aim to reduce the risk associated with temporary drainage
01:46solutions remaining in place for longer than anticipated, review ways in which tamper operators
01:52could be assisted in discovering buried services, and reduce the likelihood that buried services
01:58are struck during track maintenance by ensuring staffing levels are sufficient to comply with
02:03procedures.
02:04A further recommendation addressed to the Environment Agency, working in conjunction
02:09with Westmoreland and Furness Council, the Marine Management Organisation, Network Rail
02:15and other local stakeholders, aims to encourage timely decision-making in relation to the
02:20future of this area so that the management of floodwater does not manifest in another
02:25risk to the railway.
02:27A recommendation is also made to Eversholt Rail Leasing Ltd, the train's owner, working
02:32in conjunction with Northern Trains, the train's operator, and CAF, the train's manufacturer.
02:39This final recommendation aims to reduce the risk of a derailed train being struck by a
02:43train on the adjacent line due to an interruption of the power supply to cab communication and
02:48warning systems.

Recommended