Kamuning flyover repair starts on May 1

  • 5 months ago
Kamuning flyover repair starts on May 1

Metropolitan Manila Development Authority acting chairman Romando Artes presides over a meeting with the representatives of the Department of Public Works and Highways on the repair of the Kamuning flyover in Quezon City slated on May 1, 2024.

The repair will partially close the flyover for 11 months.

Motorists were advised to use alternate routes during the duration of the repair.

Video by John Orven Verdote

Subscribe to The Manila Times Channel - https://tmt.ph/YTSubscribe

Visit our website at https://www.manilatimes.net


Follow us:
Facebook - https://tmt.ph/facebook

Instagram - https://tmt.ph/instagram

Twitter - https://tmt.ph/twitter

DailyMotion - https://tmt.ph/dailymotion


Subscribe to our Digital Edition - https://tmt.ph/digital


Check out our Podcasts:
Spotify - https://tmt.ph/spotify

Apple Podcasts - https://tmt.ph/applepodcasts

Amazon Music - https://tmt.ph/amazonmusic

Deezer: https://tmt.ph/deezer

Tune In: https://tmt.ph/tunein

#themanilatimes
#philippines
#mmda
#roadwork
Transcript
00:001.260 million, nagbayad na po ako ng penalty, so nagbayad na po sila ng penalty na 1.260 million.
00:09525 linear meter, 17 span, pero identify lang po namin kung anong gagawin na i-redact.
00:18Ang contract duration po ito is 365 days, one year, pero yung redacting po is gagawin po for six months.
00:27At buong pabuhan po ng traffic po yung 12 months, kasi ang majority of scope po nito is nasa ilalim.
00:332,000 minor lang po talaga yung redacting, pero ito po kasi yung pinakamalaking impact sa traffic.
00:39Yung neighbors po po sa ilalim, wala naman siya maging-impose ng traffic, kasi more on carbon fiber and restrainer po yung ilalim niya sa ilalim.
00:47So at least po, ang pagsusunod na po is yung bus lane, or ang ma-open naman po is yung private.
00:56... so hindi ma-equal dyan sa lugar na yan. Yan, ang ating existing na robo-ailings.
01:03May mga roadside na tayo ang kompleto na so mas madaling, aside dun sa ginawa nila, ang lalabas nandun yung mga local traffic doon sa lugar.
01:11Pero kung marayo ang pumunta, eto na ang ating mga robo-ailings na gawin.
01:15Hilaan po.
01:17So short, will only be maximum six months, not 11 months?
01:22Yes po.
01:23So within five months, sa ilalim naman gagawin, will not affect yung flow ng traffic?
01:28Yes po.
01:29Dahil after, within six months, mga pupuksan natin siya?
01:32Yes po.
01:33... collapse yung mga lalabas, yung sa may malapit sa approach.
01:36So ito kasi is, nag-ikot ang JICA, so in-identify niya yung mga critical bridges sa Queen NCR at kasama yung family flyover.
01:45So yung nangyari ng 2022, sir, is emergency fund po yan.
01:49So iba pa po ito sa JICA po, sa research ng JICA po?
01:53Yes po.
01:54Tapos...
01:54Tapos support traffic na po siya.
01:56Okay. So ano po yung gabi niyo sa remaining five months para...
02:01Sa ilalim po? Actually ang major scope po talaga is yung ilalim.
02:06So itong re-decking po is minor scope lang talaga, kaso may mga medyo malaking effect talaga yung sa traffic.
03:12Thank you.