Pembangunan proyek pembangkit listrik tenaga minihidro (PLTM) yang direncanakan PT Terregra Asia Energy Tbk (TGRA) molor dari target.
Manajemen Terregra menjelaskan, keterlambatan pembangunan proyek-proyek mini hydro power plant disebabkan kurangnya dana hasil penawaran umum perdana saham atau initial public offering (IPO).
Manajemen Terregra menjelaskan, keterlambatan pembangunan proyek-proyek mini hydro power plant disebabkan kurangnya dana hasil penawaran umum perdana saham atau initial public offering (IPO).
Category
📺
TVTranscript
00:00MiniHydro Power Plant
00:05The construction of the MiniHydro Power Plant, or PLTM,
00:08was planned by PT Teregra Asia Energy,
00:11TBK, or MITEN,
00:12with TGRA MOLOR shares from TARGET.
00:15Teregra's management explained
00:16the delay in the construction of the MiniHydro Power Plant
00:19due to the lack of IPO funds.
00:24MiniHydro Power Plant
00:27The construction of the MiniHydro Power Plant, or PLTM,
00:31was planned by PT Teregra Asia Energy,
00:33TBK, or MITEN,
00:35with TGRA MOLOR shares from TARGET.
00:38Teregra's management explained
00:40the delay in the construction of the MiniHydro Power Plant
00:43due to the lack of IPO funds.
00:48When the listing was launched on May 15, 2017,
00:52TGRA managed to raise Rp 110 billion.
00:56Meanwhile, the budget for the five projects
00:58that have a PPA, or Power Per Case Agreement,
01:01with a total capacity of 43.8 MW,
01:04reached Rp 1.5 trillion.
01:08The management considered
01:09a request for an explanation on December 28.
01:12The management explained
01:13that until now, the main obstacle facing Perseroa
01:15is the aspect of liquidity and equity
01:18that is needed to implement the construction
01:20of the Hydro Power Plant projects owned by Perseroa.
01:24Despite this, Perseroa has obtained
01:26strategic investor funds
01:28to fund the projects in April 2024.
01:31However, the construction of PLTM SISIRA
01:33will start in Q1 2025.
01:36PLTM BATANG TORU III and PLTM BATANG TORU IV
01:39in Q3 2025,
01:41and PLTM RAISAN NAGA TIBU
01:43and RAISAN HUTA DOLOK
01:45will be targeted from Q4 2025.