• 4 months ago
Sunkishala Project Wall Collapse Issue : నాగార్జున సాగర్ జలాశయంలో భారీగా వరద రావడంతో ఒత్తిడి పెరిగి, సుంకిశాల ప్రాజెక్టు సైడ్ వాల్ కూలిపోయిందని జలమండలి స్పష్టం చేసింది. 5 నిమిషాల వ్యవధిలోనే గోడ కూలిందన్న జలమండలి, గోడను సదరు నిర్మాణ సంస్థే పునర్మిస్తుందని తెలిపింది. అందుకు అవసరమైన ఖర్చును నిర్మాణ సంస్థే భరిస్తుందని వెల్లడించింది. ఈ ఘటన వల్ల హైదరాబాద్‌ తాగునీటి సరఫరాకు, ఎలాంటి ఆటంకం కలగదని జలమండలి వివరించింది.

Category

🗞
News
Transcript
00:00In Hyderabad Mahanagara Prajala Daharthi Teeruchenduku, Nalgonda district, Peddavuram mandala,
00:06Jalamandali gave a detailed explanation on the sidewall cooling incident in the project built by Sunkisala Vada.
00:11This project was approved by the Megha Engineering Samstha Tender and
00:15Sampu Pump House 3 Tunnels in Intech Well,
00:18Pump House Super Structure is being built.
00:20Jalamandali revealed that 60% of the work of Sunkisala project Intech Well,
00:2370% of the work of Pumping Main,
00:25and 40% of the work of Electromechanical is completed.
00:29The project was built by Jalamandali to provide water supply to Hyderabad constantly in the rainy season.
00:38As the work began in July 2021,
00:41it was found that the sidewalls on the side of the reservoir tunnel were completed in July 2023.
00:47By December 2023,
00:49a total of 4 sidewall blocks,
00:513 sidewall blocks were completed up to the full level of the reservoir.
00:56When the floor level of Sampu was 137,
00:58it was stated that the construction was completed in 43 meters.
01:01By January 7,
01:03the work was completed up to the 4th sidewall block roof slab level in Jalamandali.
01:09The agency decided to complete the middle tunnel with the intention of providing water by the next summer.
01:15As per the agency, a gate was arranged on the Sampu side of the tunnel.
01:18The mud on the side of the reservoir was removed.
01:20The agency felt that the reservoir would be delayed.
01:24The gate fixing work was done for the middle tunnel.
01:27On July 29, 30 and 31, the gate construction work was carried out.
01:31At that time, the water entered the tunnel with a flow of 3.5 lakh cubic meters to the Nagarjuna Sea at a time.
01:38The sidewalls, which were adjacent to the tunnel gate, collapsed.
01:42Jalamandali stated that all this happened in just 5 minutes.
01:47The reservoir Sampu is filled with complete mud.
01:50Jalamandali stated that the sidewalls, which were damaged after the current water level was reduced,
01:54would be rebuilt by the construction agency at its own expense.
01:58It was prioritized that the reconstruction work would cost up to 20 crores.
02:12Jalamandali clarified that an inquiry committee was arranged with high-ranking engineers at the board level on that incident.
02:19According to the inquiry committee, Jalamandali will be the revenue director and project director.
02:25Jalamandali said that the committee will take decisions based on the committee's request and that the work to be completed in March could be delayed for another two months.
02:34Due to this incident, Jalamandali said that there will be no threat to the water supply in Hyderabad.
02:39Jalamandali said that the current water supply will continue as usual until next year.
02:49For more UN videos visit www.un.org

Recommended