Emiten energi terbarukan, PT Arkora Hydro Tbk (ARKO) menargetkan percepatan pembangunan dua proyek pembangkit listrik, yakni Proyek Kukusan, Lampung dengan kapasitas 5,4 megawatt dan Proyek Tomoni, Sulawesi Selatan berkapasitas 10 megawatt.
Presiden Direktur ARKO, Aldo Artoko mengatakan, masing-masing progress konstruksi kedua proyek tersebut sudah mencapai 49,9 persen dan 12,2 persen pada November 2024. Kedua proyek diperkirakan rampung pada semester II-2025 dan 2026.
Presiden Direktur ARKO, Aldo Artoko mengatakan, masing-masing progress konstruksi kedua proyek tersebut sudah mencapai 49,9 persen dan 12,2 persen pada November 2024. Kedua proyek diperkirakan rampung pada semester II-2025 dan 2026.
Category
📺
TVTranscript
00:00PTR Kora Hydro Tbk
00:05PTR Kora Hydro Tbk is targeting the acceleration of the development of two electric power plants
00:10which is targeted to be completed in 2025 and 2026.
00:14The acceleration is in line with the optimism of the development of renewable energy in Indonesia.
00:20PTR Kora Hydro Tbk
00:23PTR Kora Hydro Tbk is targeting the acceleration of the development of two electric power plants
00:30which is targeted to be completed in 2025 and 2026.
00:40President-director of PTR Kora Hydro, Aldo Artoko, in an official statement said
00:45the construction progress of the two projects has reached 49.9% and 12.2% per November 2024.
00:55Aldo added that the steam project and the Tomo project are targeted to be completed in 2025 and 2026.
01:05At present, PTR Kora Hydro Tbk has a total capacity of 42.8 MW
01:12of the three projects that have been operated, namely the Cikopo-Jawa Barat project with a capacity of 7.4 MW,
01:19the Tomasa-Sulawesi-Tengah project with a capacity of 10 MW,
01:23and the Sulawesi-Tengah project with a capacity of 10 MW.
01:28The total capacity is also contributed by two projects that are in the construction stage,
01:33namely the Kukusan Lampung project and the Tomoni-Sulawesi-Selatan project.
01:38The fifth project to generate electricity uses direct river flow.
01:43With the target of the estimated electricity production this year for the three projects that have operated as large as 118.2 GW per hour
01:52and is targeted to grow as large as 49.5% year-on-year to 176.7 GW per hour
02:00in 2025 after the construction of the Kukusan Lampung project next year.
02:05Aldo said he was optimistic about the development of the latest energy sector in Indonesia
02:11which is committed to supporting the government's target,
02:14such as the energy emission target, net zero emission, and energy supply.